Before the floor is delivered on site, all wet works (such as: concrete works, plastering, mudding) should be finished according to the good building practice and the building should be thoroughly dried. Storage, fitting and its further exploitation should take place under optimum conditions:
> 45-60% air humidity
> temperature +18 ÷ 22°C
> wall humidity up to 3%
ACCLIMATIZATION
The humidity of substrate for the assembly should equal as follows :
> wooden up to 10%
> concrete up to 1,5% according to the CM method, up to 3% according to the dry oven test
> anhydrite concrete up to 0,5% according to the CM method, up 1,5% according to the dry oven test
> concrete substrate should be dry, even and fulfil the following mechanical conditions:
> pull off test 1 MPa
> compression test minimum 25 MPa
In case of the under-floor heating it may be necessary to heat the screed.